Following our last update in May, the piling works have now been completed which has allowed for the first concrete pour to begin. Due to it’s size, the crew will be pouring the raft slab in four stages.
Rawcorp have completed the detailed excavations for footings and inground service mains. The crews are now focusing on forming up the second concrete pour and finalising the crane base.
Over the next few weeks, the crews will begin pouring the columns, working on the perimeter blockwork retaining walls, and continuing on with the raft slab.