Rawcorp continue to progress works at Northshore despite the continued extreme wet weather that much of South-East Queensland is experiencing.
To combat the extreme weather conditions, the crews have installed additional dewatering systems across the site, by doing so they’ve been successful in expediting the drainage as well as mitigating down time.
The bulk earthworks are now complete, along with the construction of the piling rig platform and perimeter piling. The crews are now focusing on the foundation piling which will continue over the next month and once completed construction of the ground raft slab will immediately begin.