Rawcorp are currently completing the final round of painting and carpet installation for the upper levels, with the first round of apartment cleaning occurring through the building.
Defect inspections by one of Queensland’s largest third-party building inspection companies, Handovers.com, are well underway. Trades are following closely with any rectification works.
The expected Practical Completion date continues to be highly impacted by erratic weather on external works and also the delivery and installation of the transformer by Energex. These have delayed the ability for the power supply to be switched over to the grid’s permanent power.