Since our last construction update, the Level 5 slab has been poured. Rawcorp are now focusing on finalising the steel & services in preparation for the Level 6 concrete pour which will occur in the next few days.
Once the Level 6 concrete pour is complete, the crews will begin installing precast columns, façade panels, blockwork walls and balconies. Inside the apartments, sheeting is underway on Level 2, whilst the internal fitouts have commenced on Level 3.
Throughout the lobby and ground floor communal areas the large floor to ceiling windows & doors have been installed, with partition frames complete and ready for wall & ceiling installation.