Externally, the installation of the rooftop mechanical plant is nearing completion, while all balustrades & glazing are now complete.
As the staged removal of the scaffolding is now underway, the towers’ distinctive architectural design is being revealed. Once the final sections of the screens are installed, the remainder of the scaffolding will be removed.
Meanwhile on ground level, waterproofing of the planters is underway, with landscaping nearing completion. Additionally, the signature entry arches on Mawarra & Brooke Street are standing proud, with works on the street frontage underway.
Internally, the builders clean & defecting is occurring on Level 1 to 3, while kitchen stone benchtops are being installed on Level 4. The common areas have been sheeted & painting has begun.
Further up the tower, joinery has commenced on Level 6, as tiling & painting also continues.