Palm Beach Residences is a hive of activity at the moment, with works occurring across every level.
Tiling on levels 2 & 3 is nearing completion while joinery fitout commences.
Crews on levels 4 & 5 are completing the internal sheeting as well as commencing the carpentry fit out.
On level 5, the internal framing & services rough-in are nearing completion, whilst on level 6 the drainage has been completed, with party walls & window installation now progressing.
Level 7 is also taking shape, with the formwork now stripped and drainage installation commencing.