As we all know, we’ve been experiencing extreme wet weather across much of the east coast of Australia over the past month.
Despite this, Rawcorp Construction has ramped up construction activity on Saturdays to mitigate the impact to the program as much as possible.
Rawcorp Construction has now completed the level 1 ground floor slab, bio basin, and the first residential level of the building including the extensive podium planters.
Installation of vertical precast columns spanning levels 2 to 4 is also complete, with blockwork walls and columns to level 2 well underway.