As the roof slab nears completion, crews will begin installing the feature precast arches as they continue works internally & externally.
This month, the internal & external works have seen considerable progress across each level. The lower levels are coming to life with the completion of tiling, shower screens & kitchen installs. Additionally, rendering & painting of balconies are at various forms of completeness up to level 4.
Crews on levels 5 & 6 are seeing the installation of drainage, party walls & windows. Meanwhile, further up the tower, formwork has been stripped from level 7.