Over the past month, crews have completed the ground floor slab, as well as the first portion of the Level 2 slab. Crews are now focusing on the Level 3 structural slab.
Due to the sheer size of each level, the structural decks are being poured in 2 stages. This staged approach helps speed up the completion cycle of each level.