Crews continue to progress up the tower, having recently completed the Level 5 concrete pour. Preparations for the Level 6 concrete pour are well underway with crews focusing on the installation of concrete columns, precast panels, and formwork.
The construction hoist has been commissioned, providing crews improved access between the levels.
The initial phase of services installation has begun in the Level 3 residential units, including the erection of the internal steel frames with electrical, plumbing, sprinkler and mechanical rough-ins.
Meanwhile, wall framing and lining is underway in the Level 3 lobby and communal facilities at the southern end of the building, including the office suites, cinema and gym.
Externally, the staged removal of the podium scaffolding has commenced, revealing sections of the building’s facade.